SunGuide

Link to home page

Inside This Issue

February 2002


Florida Transportation Commission

ITS America 2002

ITS Corridor Master Plans and ITS Program Plan

511 Traveler Information

TMC Software Study

Roadway / Weather Information Systems

Florida Fiber Network

CVO/CVISN

I-4 Corridor Invitation to Negotiate

Training Opportunities

ITS Progress Report
District 1

District 2
District 3
District 4
District 5
District 6
District 7
Turnpike District

Announcements

FDOT ITS Office Contacts

Link to home page

FDOT Logo

Florida Department of Transportation
ITS Office
605 Suwannee Street, MS 90
Tallahassee, Florida 32399-0450
(850) 410-5600

I-4 SMIS Fiber Optic Connection to DASH (410724-2-52-01)
Extension of the I-4 SMIS 72 Fiber Optic Communication Network from SR 44 to DASH
Approx. Completion: Construction begins July 2002
Contact: Ms. Anne Brewer / (386) 943-5319

I-4 Auxiliary Lanes from SR 536 to SR 528 (405515-1-52-01)
Relocating and/or replacing the existing I-4 SMIS ITS infrastructure. Includes 72 SM Fiber Optic Communication Network. Creates redundancy in the system.
Approx. Completion: September 2002; Currently under construction
Contact: Mr. Scott Silva / (386) 943-5317

I-4 Auxiliary Lanes from SR 528 to SR 482 (4107032-1-52-01)
Relocating and/or replacing the existing I-4 SMIS ITS infrastructure. Includes 72 SM Fiber Optic Communication Network. Creates redundancy in the system.
Approx. Completion: Contractor has been selected for this project
Contact: Mr. Scott Silva / (386) 943-5317

I-4 Auxiliary Lanes from SR 423 to SR 436 (242499-1-52-01)
Relocating and/or replacing the existing I-4 SMIS ITS infrastructure. Includes 72SM Fiber Optic Communication Network. Creates redundancy in the system.
Approx. Completion: October 2003; Currently under construction
Contact: Mr. Scott Silva / (386) 943-5317

I-4 Auxiliary Lanes from SR 435 to Turnpike (242496-1-52-01)
Relocating and/or replacing
the existing I-4 SMIS ITS infrastructure. Includes 72 SM Fiber Optic Communication Network. Creates redundancy in the system.
Approx. Completion: In Design
Contact: Mr. Scott Silva / (386) 943-5317

I-95 Daytona Smart Area Highway (DASH)
Existing ITS; cameras, detectors, DMS on I-95 and I-4 (Daytona Beach Area).
Approx. Completion: Completed
Contact: Ms. Anne Brewer / (386) 943-5319

 

I-95 Phase 2 I-95/SR 528 Hurricane Evacuation System (22250-1-52-01)
Construct ITS elements along I-95 and SR 528 to assist in the evacuation of East and South Florida. Includes 72 SM Fiber Optic Network, 12 CCTV, 6 DMS 13 detector stations.
Approx. Completion: September 2002; Under Construction
Contact: Mr. Scott Silva / (386) 943-5317

I-95 Six Lanes Volusia County I-95 / I-4 / US 92 (242715-1-52-01)
Upgrade of DASH in Volusia County. Includes the relocating and/or replacing of existing DASH ITS infrastructure. Includes 72SM Fiber Optic Network.
Approx. Completion: Currently Under Bid
Contact: Ms. Anne Brewer / (386) 943-5319

I-95 Phase 3 (410730 -1- 52-01)
Expansion of DASH in Volusia County. North to US 1 and South to SR 44.
Approx. Completion: Unfunded
Contact: Ms. Anne Brewer / (386) 943-5319

I-95 Phase 4 (410729-1-52-01)
Expansion of DASH in Flagler County, Brevard County, and Volusia County.
Approx. Completion: Unfunded
Contact: Ms. Anne Brewer / (386) 943-5319

I-4 Road Rangers - Motorist Assistance Program (406358-1-54-01)
Continued and Expanded Program between District 5 and LYNX.
Approx. Completion: Underway
Contact: Ms. Jennifer Heller / (386) 943-5322

•• District Six • •

Advanced Traffic Management Systems

ATMS - Signal System Upgrade (249908-1 thru 249910-1 / Phase A; 249907-1 / Phase B)
This is a Miami-Dade Countywide Project. It involves upgrading the Traffic Control System (TCS) to an ATMS capable of handling 4,096 controllers, implementing national ITS standards, transitioning the County from leased phone lines, and replacing aging system. Phase A is Design - Alpha Test 16 site locations. Phase B is Implementation. Phase A started October 1996 & Phase B begins May 2003.

 

Approx. Completion: Phase A in July 2003 and Phase B in December/2009
Contact: Angel Reanos / (305) 499-2483

Advanced Traveler Information Systems

Traveler Information (405663-1)
Provides uniform, multi-modal, real-time traveler and traffic information in the tri-county region (Miami-Dade, Broward, and Palm Beach) under the SunGuide program. There is a Traveler Information Center located in the Golden Glades Interchange Area, Interactive Voice Response telephone system, and website (smartraveler.com) already operational. We are working on providing snapshots of real-traffic conditions on the web. A supplemental agreement has been signed to implement a Consumer Information Network. Services commenced on November 2000.
Approx. Completion: November 2005
Contact: Rene deHuelbes / (305) 470-5341

Transportation Management System

I-95 Intelligent Corridor System Package B (2516821-52-01)
Installation of 8 FDMS, 8 ADMS, 54 detector stations (42 RTMS and 12 loops), 22 dynamic and 5 blank out trailblazers, 14 ESS, and 22 ramp signaling sites along I-95. Notice to Proceed was issued on February 4, 2002. The Procurement Period is 241 calendar days and the contract start time is September 1, 2002 with a construction time of 1,350 calendar days.
Approx. Completion: December 2005
Contact: Jason Chang / (305) 470-5331

I-95 Intelligent Corridor System Package C (2502381-52-01)
Construction of a 32,000-square foot SunGuide Transportation Management Center (STMC) in the southern end of the existing FHP Al Lofton Building grounds. Construction time of 471 days. No excuse bonus of $0.5 million to be awarded if building is finished by 375 days.
Approx. Completion: April 2003
Contact: Jason Chang / (305) 470-5331

SR 826 (Palmetto Expwy) East/West ITS Deployment (249719-2)
Design Build Project to be constructed concurrently with ITS Deployment in the Upper Florida

 